Product Launch Process — What Needs to Be Done

The 7-step execution sequence common to every new product launch. Regardless of which team is PIC (see Section 1), this sequence proceeds without skipping any step

Process at a Glance — 7 Step Summary
STEP Description Owner Related Status
1 PLM Project Creation · PLM Product Development Request Creation PLM PART Done
2 Ingredient Review · Artwork Copywriting · Specification Setup · Design Brief R&D/TQR/Design Done
3 Material Code Generation · Barcode Generation · Packaging Code Generation Global SAP Done
4 Receive Entity P&L · Review Product/FOC Cost-Profit Planned
5 Launch Approval · Business Correspondence Planned
6 Design Execution · Design Review Circulation · Design Release Planned
7 Transition Timing Discussion · Packaging Material Inbound · BOM Setup Planned
The PIC for STEP2 (Artwork Copywriting) and STEP6 (Design) may shift between HQ and the US Team depending on the launch case (see Section 1 Work Division Framework)
OwnerThe core working team that actually executes the process
RelatedTeams whose approval or alignment is needed
STEP1
  1. PLM Project Creation
  2. PLM Product Development Request Creation
Owner: PLM PART Related: R&D
STEP2
  1. Ingredient Review (formula-change cases only)
  2. Artwork Copywriting
  3. Specification Setup (new packaging material cases only)
  4. Design Brief
Owner: R&D/TQR/Design
STEP3
  1. Material Code Generation
  2. Barcode Generation
  3. Packaging Code Generation
Owner: Global SAP Related: Production/Accounting/Process
STEP 4 (Planned)
  1. Receive Entity P&L
  2. Review Product/FOC Cost-Profit
Related: Management/Finance
STEP 5 (Planned)
  1. Launch Approval
  2. Business Correspondence
Related: Corporate Operations/Packaging Procurement/Inventory Policy/PPC/Management-Finance/Soup Production/Noodle Production
STEP 6 (Planned)
  1. Design Execution
  2. Design Review Circulation
  3. Design Release
Related: Corporate Operations/Packaging Procurement/Inventory Policy/PPC/Management-Finance/Soup Production/Noodle Production
STEP 7 (Planned)
  1. Transition Timing Discussion
  2. Packaging Material Inbound
  3. BOM Setup
Related: Packaging Procurement/Inventory Policy
1
PLM Project Creation
1) PLM Project Creation
Task Details (To Do)TimelineRemarks
Create a new PLM project for the new launch item1 Day
2) PLM Product Development Request
Task Details (To Do)TimelineRemarks
Initiate a product development request to generate the P-Code *Material code can only be generated after the P-Code is created1 WeekProcess Flow: Create Request → R&D Approval → P-Code Generation
2
Ingredient Review · Artwork Copywriting · Specification Setup · Design Brief
1) Ingredient Review (formula-change cases only) *Halal Certification Check
Task Details (To Do)TimelineRemarks
Request Master Ingredient List *When a statement for a new raw material is required (e.g., request an official memo when selling Samyang Buldak Bokkeummyeon into Canada)Min. 1 MonthSubmit Official Work Request
Request Nutritional Analysis Report2 WeeksSubmit Official Memo Request
2) Artwork Copywriting
Task Details (To Do)TimelineRemarks
Ingredients: Draft the ingredient statement wording under TQR, based on the finalized Master Ingredient List1 Week
NF: Draft the Nutrition Facts (NF) format under TQR, based on the Nutritional Analysis Report1 Week
3) Specification Setup (new packaging material cases only)
Task Details (To Do)TimelineRemarks
Requested when launching a new specification/size3 WeeksSubmit Email Request
4) Design Brief
Task Details (To Do)TimelineRemarks
Draft and prepare the Design Brief file1 WeekAttachment Files (PPT/EXCEL)
Official memo: Submit internal workflow approval for the Design Brief1 DaySubmit Official Memo via Groupware (To: Global Design Team)
3
Material Code · Barcode · Packaging Code Generation
1) Material Code Generation
Task Details (To Do)TimelineRemarks
Circulate the Material Code generation/expansion file to relevant departments, then upload to SAP1 WeekAs needed
2) Barcode Generation
Task Details (To Do)TimelineRemarks
Generate the UPC barcode via KorEAN (GS1) (*If using an EAN barcode, the number is issued directly in SAP)1 WeekAs needed
3) Packaging Code Generation
Task Details (To Do)TimelineRemarks
Request code generation for each item10 DaysAs needed
4
Product/FOC Request · Setup · Registration
1) Product/FOC Request
Task Details (To Do)TimelineRemarks
Deliver detailed product specs (packaging composition, expected launch channels, demand forecast, target production month, etc.) to HQ MKT3 DaysSubmit Email Request
2) Product/FOC Setup & Final Cost Request
Task Details (To Do)TimelineRemarks
(If needed) Request final cost verification → Proceed with Product/FOC setup together with HQ MKT3 WeeksSubmit Email Request
3) Product/FOC Registration
Task Details (To Do)TimelineRemarks
Complete SAP entry for the agreed Product/FOC price indicators3 Days
5
Launch Approval · Business Correspondence
1) Internal Business Communication
Task Details (To Do)TimelineRemarks
Launch Approval
Business CorrespondenceRelated: Corporate Operations/Packaging Procurement/Inventory Policy/PPC/Management-Finance/Soup Production/Noodle Production
Timeline details are not yet available in the source material
6
Design Finalization & Approval
1) Design Finalization & Approval
Task Details (To Do)TimelineRemarks
Execute design development → Circulate for internal review/feedback → Order final design files for packaging production2 Weeks
Submit official internal approval/workflow memo for final design sign-off2 DaysSubmit via Groupware
7
Transition Timing Discussion · Packaging Material Inbound · BOM Setup
1) Transition Timing Discussion
Task Details (To Do)TimelineRemarks
Discuss the timing of transitioning from the existing SKU to the new SKURelated: Packaging Procurement/Inventory Policy
Timeline details are not yet available in the source material
2) Production & Inbound Logistics
Task Details (To Do)TimelineRemarks
Packaging Material Inbound — Manage logistics and delivery confirmation for packaging materials arriving at the plant1 Week
3) BOM Setup
Task Details (To Do)TimelineRemarks
BOM (Bill of Materials) setup
Timeline details are not yet available in the source material

Where Section 1 and Section 3 Connect

The 7-Step process is the same execution sequence for any launch, while the Work Division Framework (Section 1) determines who is responsible for that execution. Depending on which of the 9 Task Purposes this launch falls under, the PIC for Step 2 (Artwork Copywriting) and Step 6 (Design) may shift between HQ and the US Team.